A Florida restaurant answers to two layers of government. DBPR, the state food regulator, licenses it, while the local building department, fire marshal and utility each hand out their own approvals. Neither layer stands in for the other, so the work goes in sequence and every approval stays at the restaurant. Commercial Kitchen 101 explains the sequence and passes build-out requests to local companies.
The offices involved
- DBPR, Division of Hotels and Restaurants. It licenses the restaurant and reviews the kitchen plan. The customer line is 850.487.1395.
- The building department. It issues the building permit and checks plans against the Florida Building Code. Before a permit is issued, a certified fire safety inspector must find that the plans meet the Florida Fire Prevention Code and the Life Safety Code.
- The fire marshal. Fire protection is this office's area: hood suppression, extinguishers, exits, and alarms or sprinklers where required.
- The water and sewer utility. Grease trap and interceptor rules come from here and vary by city and county. Depending on the site, the Department of Health, FDEP or the local utility also approves wastewater for the seating.
DBPR says its expertise lies in state requirements and urges applicants to contact local officials about city and county rules.
When DBPR plan review applies
Review is required for a space that is newly built, converted from another use or remodeled. It also applies after a closure of at least 18 months, and when a menu change brings different equipment or changes the concept. A licensed space with no changes does not need it, nor does a shared licensed kitchen. On a septic system, the Department of Health or FDEP approves first. A private residence cannot host food service.
The application comes with:
- A completed application form.
- A floor plan to scale, equipment labeled.
- A sample menu.
DBPR states that online applications get a response within 30 days, and a variance request within 90 days or 30 for an emergency. Plan review has no fee.
A local company can take it from here. One form, free for restaurants.
Get connectedWhat the drawing shows
DBPR's packet lists the items, among them:
- Labeled work areas and storage.
- A utility sink and handwash sinks.
- A three-compartment sink, or a commercial dishwasher.
- Exits and door swing.
- The automatic suppression and hood system.
- The dumpster location, on a non-absorbent surface.
- A grease trap, when it sits outside.
The fire protection entries on the DBPR plan exist for reporting. DBPR notes that Class K extinguishers and automatic hood suppression are required where grease-laden vapors or smoke are produced, and it passes possible fire violations to the State Fire Marshal or local fire authority. Those items do not sink a DBPR plan, so the fire marshal settles them on a separate track.
Seat counts are not DBPR's to approve. The wastewater approval and the local fire authority cap the seating.
An approved plan stays valid for 18 months, and one written extension of up to six months can be requested before expiry. Approval does not promise a license.
Sequence
- Check the space. The zoning office confirms a restaurant is allowed, and the utility is asked about grease interceptor and seating limits.
- Order engineered drawings for the hood, grease duct, makeup air and suppression system, using the hoods and exhaust and fire suppression guides.
- Create a DBPR online account, submit plan review with the license application and pay the fees.
- Apply for the building permit. Some building departments run their own plan review, so ask which drawings are wanted.
- Begin construction. Florida law lets a building department permit foundation or partial work before full plan review ends, at the holder's risk.
- Have a licensed company install and test the hood suppression system and extinguishers, per the fire extinguishers guide.
- Clear the local inspections. Building, electrical, plumbing and fire approvals come from local offices, and each proof is kept.
- Book the DBPR licensing inspection. Serving the public waits until the inspection is passed and a temporary license arrives. The inspector sees the building, electrical, fire and plumbing approvals on site.
Schedule the hood test early, since the Florida Mechanical Code requires a performance test before final approval. It checks exhaust airflow, makeup airflow and capture of smoke or steam.
Timelines found
No single timeline for a whole project is published by DBPR or the local offices. The table lists only the review times that could be sourced.
| Step | Time that could be sourced |
|---|---|
| DBPR plan review, online application | Reviewed within 30 days |
| DBPR variance request | 90 days, or 30 days if urgent |
| DBPR approved plans stay valid | 18 months, one extension up to 6 months |
| Building permit review | Set by your building department. Ask them |
| Fire marshal plan review | Set by your fire marshal. Ask them |
License fees
The annual DBPR license is priced by seating. No seating costs $242, 1 to 49 seats cost $262 and 50 to 149 seats cost $273. The scale climbs to $357 for 500 or more seats. New businesses and ownership changes pay an added $50 application fee, and the renewal month follows the district.
Send the form with the ZIP code of the space for a build-out or new kitchen, and it goes to the number of local companies you choose (one to five).
Questions
Does a remodel require DBPR plan review?
It does, and so does a menu change that needs different equipment. A space that is already licensed and unchanged is exempt.
May construction start before DBPR approves the plans?
DBPR says plans must be approved before construction, remodeling or licensing. A building department may permit partial work early at the holder's own risk, so ask both offices first.
Which office signs off on the suppression system in a new kitchen?
The local fire marshal. A company licensed by the State Fire Marshal must install it, and it has to meet the codes Florida has adopted.
Can the doors open the day construction ends?
Only after the DBPR licensing inspection is passed and a temporary license is issued. The building, electrical, fire and plumbing approvals stay on site for the inspector.